The walls go up, January 4-5, 2012

 

January 4 was bright and beautiful.  The PreStressed crew put up 8 of the 12 panels on one day with a 130,000 pound Link Belt crane with a 120 foot boom.  Each 30,000 pound wall was lifted in place,  epoxy spiked to the foundation, and welded together.  All 12 walls were up by the next day, Thursday, January 5.

Wall erection and events following to January 21, 2012